Server migration from Transition to Production

  • Scope/Deliverables:
    • Perform gateway change at the core network switches to redirect the data center traffic to a new network farm
  • Activities:
    • Performed 6 individual migrations of Test, UAT and Production servers from transition network to new network.   Implemented live cut overs affecting 400 plus Windows and UNIX servers.  
    • Co-ordination with hundreds of users for  successful cut overs -  business users from different LOB’s and technical resources from different teams – Windows OS, AIX, Lotues Notes, Oracle, SQL, WebSphere, VMware and Power HA SMEs, MQ, application owners. Prepared cut over checklist that include pre-implementation steps, implementation steps, fall back plan, validation steps, discovery data, escalation matrix/li>
    • Prepared and presented OR procedure (Operational Readiness) to Change Management Board and Governance board 
    • Project status regularly reported using Earn Value (EV), CPI and Estimate at Complete (EAC)
  • Project Duration : 8 Months